LAS VEGAS (KTNV) — Motorists of Las Vegas, be on the lookout for more lane restrictions on Las Vegas Boulevard and Tropicana Avenue.
Most of the work occurs Sunday through Friday, evening through early morning hours.
#TrafficAlert 🚨 Motorists are advised of the upcoming lane restrictions on and around the Las #Vegas Strip for work occurring as part of #ClarkCounty's Las Vegas Blvd. Improvement Project.The schedule and related impacts listed on the map below. More: https://t.co/14d5GxJh9k pic.twitter.com/G8aDbit6oq
— Clark County Nevada (@ClarkCountyNV) October 24, 2024
Las Vegas Boulevard Work Zones – 12 a.m. to 9 a.m.
- Through Friday, Nov. 8, two lanes will alternate northbound and southbound on Las Vegas Boulevard between Reno Avenue and Bellagio Drive for utility adjustments and striping.
- Through Friday, Nov. 1, one lane is open westbound on Harmon Avenue at Las Vegas Boulevard to the Cosmopolitan parking garage entrance for paving and storm drain work.
9 p.m. to 6 a.m.
- Through Friday, Nov. 1, two lanes are open northbound on Las Vegas Boulevard from Russell Road to Four Seasons Drive for waterline work.
- Starting Sunday, Nov. 3, through Friday, Nov. 15, one lane will be open northbound on Las Vegas Boulevard from Clark County 215 to Sunset Road for waterline work.
Tropicana Avenue Work Zones – 8:30 p.m. to 6:30 a.m.
- Through Friday, Nov. 8, alternating two lanes are open westbound and eastbound on Tropicana Avenue from Las Vegas Boulevard to Koval Lane for utility adjustments and striping.